Project Management

Section A (Answer both questions)

SECTION A

1. Critical Path Method: Considering the project information presented in the table below:

a.  Draw the network diagram (5 marks)

b.  Calculate the total duration of the project (5 marks)

c.  Identify the critical path of the project (5 marks)

d.  What is CPA, give examples (10 marks).

 

(30 marks)

 

2. Project Monitoring (Earned Value Analysis): You are responsible for a project within the UKSOL a multinational from the Energy Solar Industry . UKSOL recruited you to produce 300 units of PV-Solar panels over 30 days. You planned to produce at a steady rate of 10 PV-Solar per day. The budget cost per PV-Solar is £510. The total project budget is £153.000. At the end of day 20 you have made 117 PV-Solar at a cost of £120.000 (AC)

a)  Calculate the Planned Value (PV) and the Earned Value (EV) of the project- (5 marks)

b)  Calculate the Schedule Variance (SV) and the Schedule performance index (SPI)- (5 marks)

c)  Calculate  the  Cost Variance  (CV)  and  the  Cost  performance  index (CPI) -(10 marks)

d)  Calculate and explain the Estimate at Completion (EAC)- (10 marks)

30 marks

 

Please turn over for section B


Section B (Choose 2 out of 3 questions)

Background information

Jaguar Land Rover (JLR) is the UK's largest automotive manufacturer, built around two  iconic  British  car  brands:  Land  Rover,  the  world’s  leading  manufacturer  of premium all-wheel- drive vehicles; and Jaguar, one of the world’s premier luxury sports saloon and sports car marques. The company employs almost 38,000 people globally and supports around 275,000 more through our retailers, suppliers and local businesses.  Manufacturing  is  centred  in the  UK, with  additional  plants  in  China, Brazil and India. JLR is currently planning a project for its expansion in South Africa or Mali, you, as a project manager require to purpose two of the below topics to ensure JLR produce the best decision.

 

3. Essential skills: Critically discuss the type of essential skills a project manager should have to be able to successfully manage a project. Provide examples and support from reputable sources and explain how these skills could contribute to the project success. (20 marks)

 

4.   Project  selection:   Present  and  compare  different  strategies  available  to organizations in selecting the most appropriate projects to fund. Support your arguments with valuable sources, research, journals, etc.  (20 marks)

 

5. Project resources (20 marks).

a. What is the purpose of resource management for the JLR project? (10 marks)

b. Explain the project resources phases to be considered in the development of the JLR project. What is the purpose of each of these phases, and how do they help to maximise the productivity and efficiency of the project?   (10 marks)