Aircraft Electric Power System Overview: System Description and Specifications

1.  Introduction

This document focuses on the power distribution system of an aircraft’s electric power system as part of the  Multiscale System Center (MuSyC) avionics challenge problem.   As an aircraft becomes increasingly more electric (i.e., hydraulic and pneumatic systems are replaced with electric systems), the electric power system becomes increasingly critical for safe operation. The electric power system typically consists of a combination of generators, contactors, buses and loads. Primary power generation elements include batteries, auxiliary power units (APU), generators connected to the aircraft engine, and a ram air turbine (RAT) used for emergency power. Power is distributed via one or more buses and connection of generators to loads is routed  by way of a series of electronic control switches  (contactors).  Primary electric  loads include   communications   and   computing   systems,   electrically-driven   actuation   systems (including electro-hydraulic systems), anti-ice and/or de-ice systems, and lighting systems.  In this report, we discuss design specifications, while focusing on the single-line diagram shown in Figure 1.

2.  System Description

In what follows, we  provide a  brief description of the electric  power system, starting from  its  main components.1

2.1 Components

●    Generators

○    DC generators are regulated by means of a commutator, which enables an AC sine wave output voltage to be full-wave rectified and smoothed to a steady DC voltage.

○    AC generators include a permanent magnet generator (PMG), excitation stator surrounding an excitation  rotor containing rotating diodes, and a  power  rotor encompassed by a power stator. The PMG generates variable frequency power sensed by the control and regulation section of the generator controller unit.

○    AC/DC voltage levels should be compliant with the standards (for example, 115-

120 VAC,  28 VDC).  Higher voltages  are  not  inherently  advantageous,  as they require more insulation. Transmission of power at higher voltages, however, is better due to lower currents, which lead to lower power losses (proportional to the squared current).

●    Buses: AC and DC power buses deliver power to a number of loads or power conversion equipment. A start bus is used for the combined starter/generator.

●   Transformer Rectifier Units: Rectifier units are used to convert three-phase AC power to DC  power.  Transformers  are  used  to  step  down  high  voltages  to  lower  voltages.  A combined transformer  rectifier  unit  both  converts  power  from  AC to  DC  as  well  as lowers the voltage.

●    Motor  Drives:  Motors  are  used  to  drive  a  valve  or  actuator  from  one  position  to another.  Typical  uses  for  motors  include  actuation  (engine  control,  trim,  flap/slat operations), control valve operation, starter motors (used to start the engine), pumps, gyroscope  motors,  and  fan  motors.  Motor  drives  can  be  used  to  control  doors, windshield  wipers,  hydraulic  pumps.  In  hybrid  systems,  hydraulic  pumps  are  only supplemental; there are also electrical alternatives.

●    Motor  Controllers:  These  are  permanent  magnets  (induction  motors)  and  require  a rotating AC source to operate.

●    Contactors:  Contactors  are  high-power  switches that  control the flow  of  power  and establish  connections  between  components.  In  particular,  contactors  can  support current level of the order of 1000 A, while relays support current levels of the order of 1

A. Contacts can be 3-phase or single phase. Critical loads lose their functionality when they experience more than 50ms power interruption. Auxiliary contacts are included in each unit to provide an “open” or “closed” contactor status to other aircraft systems.

●    External Power: This is a power supply provided when the aircraft is on the ground.

●    Batteries: Batteries are used as an electrical storage medium independent of primary generation sources. Their  main  uses  include assisting  in damping transient  DC  loads, providing  power  in  system  startup  modes,  and  providing  short-term  high-integrity power sources during emergency conditions while alternative sources are being brought online. The battery set may not be symmetric.

●    Loads:  Electrically-driven  loads  include sub-systems such as  lighting,  heating,  motors, and actuation. Some subsets of loads are critical and cannot be shed, while others can be taken offline in case of emergency.

●    Sensors: Sensors are used to monitor the status of the system and to identify possible faults. There are three important classes of sensors, namely, current sensors, voltage sensors and contactor sensors. Voltage sensors, which consist of a set of resistors, are cheaper than current sensors  (hence  preferable  in terms of cost). Contactor sensors come with the contactors, at no additional cost.

2.2 Single-Line Diagram

The  role  of  primary  distribution  is to guarantee that  primary  buses  are  correctly  powered. Figure 1 illustrates an architecture for electric starting, generation, and distribution in a more- electric aircraft. The top of the diagram shows six generators and an external power source. Each  engine  connects  to  a  high-voltage  AC  (HVAC)  generator  (blue)  and  a  low  voltage  AC emergency generator (purple). Two HVAC APUs can also serve as backup power sources, and an external source can be connected when on the ground.

Each of the three HVAC distribution panels has one or two HVAC buses, which can be selectively connected to the HVAC generators/APUs and to each other via contactors (represented by the double bars in the single-line diagram). Each panel also has its own start bus (green). The start bus can draw power from the motor drive, and is used to power on either the main generator or the APU. Once the generator comes online, the start bus is disconnected, the generator/APU then proceeds to power the main buses. HVAC Bus 1 and 4 contain two types of loads. Loads labeled  L are essential  loads and  must  remain  powered (subject to the safety specifications detailed in the following section). Loads LS  are sheddable loads and can be dropped if power supplies are insufficient. Loads include, in addition to motors and actuators, lighting, heating and cabin pressurization.

Four Rectifier Units (RUs) are selectively connected to the four HVAC buses. RU 1 and 2 are directly connected to high-voltage DC (HVDC) Bus 1, and similarly RU 3 and RU 4 are connected HVDC  Bus  2.  Each  HVDC  bus  also  has  a  battery  source  that  can  be  selectively  connected. Additionally, each HVDC bus powers a set of motor drives. HVAC Bus 2 and HVAC Bus 3 are also selectively connected to a set of transformers that convert HVAC to low voltage AC (LVAC). The LVAC system is contained in the green boxes in the diagram. The transformers are connected to a series of four LVAC buses. AC Ess bus 1 and AC Ess bus 2 are essential and should always be powered.   These   buses   are   selectively   connected   to   the   two   emergency   generators. Additionally, an external ground source can be applied to the buses for ground services and handling,  e.g.  operations  that  are  only  used  when  the  aircraft  is  on  the  ground,  and  are therefore never powered when in flight.

AC essential buses are connected to RUs converting LVAC to low-voltage DC (LVDC) as shown in the blue panels. There are four LVDC buses each with sheddable and un-sheddable loads, as well as two batteries, which may be selectively connected. Power can also be routed from the HVAC bus through transformer rectifier units to LVDC Main Bus 1 and LVDC Main Bus 2.

 

Figure 1: Single line diagram of an electric power system adapted from Honeywell Patent US 7,439,634 B2. Figure courtesy of Rich Poisson, Hamilton-Sundstrand.


3. Specifications

The requirements of the power system are generally expressed in terms of safety, availability (reliability) and performance (e.g., power quality and voltage and current levels needed for the system  to  function  properly).  Defining  specifications  is  an  iterative  refinement  process. Specifications defined by the customers and the related single-line diagram are merged into a document together with the “internal specifications” originating from the experience of the company that is in charge of integrating the power system. Such a document is compiled in English text, and may be hundreds of pages in length. On this reference document both the customer  and  the  company  agree  for  future  development.  Afterwards,  specifications  are partitioned among the main building blocks such as generators, primary distribution, secondary distribution and load management. The organization of the components into panels occurs also at this stage. In general, different components may come from different providers. The task of defining  the  specifications  and  possibly  partitioning  them  may  require  a  good  number  of experts interacting on several issues and taking decisions, mostly based on experience and a limited  amount  of  tool  support.  At  the  level  of  the  component,  further  refinement  steps include,  for  instance,  partitioning  between  mechanical  and  electrical  domains,  and  in  the electrical case, between hardware and software. Supporting tools may include, for instance, Doors (which allows managing requirements, but is not useful for formalizing requirements) as well as advanced (in-house) differential equation solvers for cyber-physical system simulation.

The basic safety principle prescribes that no single failure can cause to lose important features. Failures can be classified as in Table 1.

 

Operational hours denote the “hours of flight”. A probability of occurrence of 10-9  can also be interpreted as a Mean Time Between Failure (MTBF) of 109  hours. These probability levels are estimated via fault tree analysis and reached by using redundancy of paths in the control loop. In fact, safety constraints translate into the architecture in terms  of independence  between

hardware and software components that is  needed to guarantee a certain fault  probability. Independence  is  mostly  implemented, for  instance,  by  using  redundancy and  parallelism  of components.  As  an  example,  some  contacts  have  a  dual  controller  (Master-Slave)  or  two controllers  may  be  used  to  control  the  same  subsystem  to  be  robust  against  hardware problems. Similarly, sensors may include duplicate auxiliary contactors as shown in Figure 2, or contactors can be used in groups for redundancy, as represented in Figure 3.2  We summarize the set of safety, reliability and performance specifications as follows.

3.1 Safety

    Each generator shall be controlled by one and only one controller.

●   To avoid paralleling of AC sources, no AC bus can be powered by multiple generators at any point of time.

●    Contactor closure times are between 15-25 ms and opening times are between 10-20 ms.

●    Essential AC buses can never be unpowered for more than 50 ms. This requirement is

necessary in order for contactor switches to open or close to avoid paralleling of sources. DC buses shall never be unpowered under no fault conditions.

●    Never lose more than one bus for any single failure.

●    At least half of each type of motor drive must be working at all times.  In Figure 1, there are four A motors, which means that at least two of those motors must be powered.

   Total load must be within the capacity of the generators.

    Other safety specifications include no arcing and personal safety.

 

3.2 Reliability

●    Every component comes with a reliability level. A level of 10−5, for example, means that

one failure will occur every 105 hours. The desired system will satisfy the following probabilities:

○    The probability of losing one bus must be less than 10−5 .

○    The probability of a component failure ranges between 10−4 and 10−7 . With these components, the system must be designed to be safe up to 10−9 under all               conditions. That is, the systems must be capable of tolerating any combination of component faults that has a joint probability more than 10-9 .

●    Erroneous processors: Components could be functioning correctly, but a processor might also fail due to hardware or software faults.

●    Every level of failure should be considered in the controller - from individual components to everything connected to the controller.

 

 

 


 

 

3.3 Performance

    Priority:  Each  bus  has  a  priority  list  by  which  it  can  be  determined  which  active generator should be selected to power it. If the first priority generator is unavailable, then it will be powered from the second priority generator, and so on. A hypothetical prioritization list is shown in Table 2. For instance, the priority list for the HVAC Bus 1 prescribes that it should be powered from the first available  power source from this ordered list: high voltage left generator (Eng 1 HV), high voltage right generator (Eng 2 HV), left APU (L APU), right APU (R APU), low voltage left generator (Eng 1 LV) and high voltage external source (HV_EXT_PWR). No bus has priority over another bus, i.e. there is no notion that HVAC1 needs to be powered based on its list before satisfying HVAC2. In addition, no bus should be able to downgrade another bus’s priority source.

    System loads: The system has two kinds of loads, i.e. non-shedable (critical) loads and shedable   (non-critical)   loads.   Avionics   components,   DC   loads,   fuel   boost   pump, hydraulics and window heating are considered as non-sheddable loads. Fuel override pump, fuel jettison pump, ice rain protection unit, cooling fans and lights are considered as sheddable loads.

    Load  management  policies:  The  load  management  controller  distributes  available power to system loads and, if there is no adequate power, it shall shed the loads based on their priorities. Power is always first allocated to the non-sheddable loads and then to the sheddable  loads  by  respecting,  in all cases, the  load  priorities.  Loads that are allowed to be shed are those labeled with LS  in Figure 1. Table 3 provides a hypothetical list of sheddable loads for HVAC Bus 1. A higher shed priority number represents a load that should be shed first.

    Aircraft electric voltage levels: The electric power system shall provide electric power so that the AC voltage level is between 115 and 120 V and the DC voltage level is 28 V.

    Power quality:  Each generator  is equipped with a generator control  unit  (GCU) that monitors and regulates the generators output voltage and controls a contactor, called generator control breaker, which is used to isolate a faulty generator from the rest of the system. GCUs should be designed to meet power quality constraints.

    Pilot operation: The pilot performs engine starts/shutdown, monitors run-up and can manage loads.

    Bus Power Control Unit (BPCU): There can be one or more BPCU to control the switches (contactors) and provide  power to AC and  DC buses. The  BPCU shall be in charge of enforcing  priority  list  as  discussed  above .  It  is  also  desirable  for  the  BPCU  logic  to minimize   the   number   of   changes   of   the   contactor   status   (closed/open),   while reconfiguring the system due to faults, so that the wear and tear of the contactors can be kept to a minimum.

    Limit contactor switches: Contactor switches should be kept to a minimum to extend the life of the component. In a power transfer sequence, if a contactor starts sequence closed  and  ends  sequence  closed,  then  it  cannot  be  opened  in  the  middle  of  the sequence.