CIBC6013

CONSTRUCTION INDUSTRY PROCUREMENT

Assignment

Scenario

A client wishes to increase the gross floor area of its shopping mall due to the growing demand of commercial space.   The  mall, which was constructed 5 years ago, is a two-storey steel structure.  It wishes to undertake the vertical expansion as soon as possible. The project site in near to a primary school. Pretender/Consultant’s estimate for the project is $3,257,100.00.

In the process of seeking the suitable contractor to carry out the construction works under traditional (DBB) method; the client has advertised the tender using a competitive tendering method and clearly stated that the evaluation process will consider non-price attributes (70%) and price (30%). However, the client would like to compare different results/outcome from different tender evaluation methods.

Task 1 – Tender evaluation/report (40 Total Marks)

i.      Given the information in the  attached Appendices, evaluate the three tenders and recommend to the client the most suitable tender for the project. You are required to evaluate the tenders against each of the following tender evaluation methods:

1.   Weighted Attributes

2.   Lowest Price Conforming

3.   Brook’s Law

Note:

•    If there is any necessary communication required during this tender evaluation stage between the client/consultant and the  tenderer (s), write a formal letter to the tenderer(s) as required and submit it with this assignment.

•   The tender evaluation team have agreed to score the non-price attributes as follows:

-     Excellent = 100%

-     Very good = 80%

-     Good = 60%

-     Satisfactory = 50%

-     Poor = 40%

SUMMARY OF NON-PRICED ATTRIBUTES

S/N

Non-price Attributes

Clean      Construction

Co. Ltd.

Holy      Construction

Co. Ltd.

Pure   Construction

Co. Ltd.

1

Relevant experience

Excellent

Very good

Excellent

2

Past performance

Good

Good

Good

3

Technical skills

Excellent

Excellent

Excellent

4

Resources

Very good

Very good

Poor

5

Management     skills    &

systems

Excellent

Excellent

Very good

6

Financial capability

Good

Good

Excellent

7

Workload

Good

Very good

Excellent

•    During the tender evaluation process, you noted that the specification for building wrap which is Dripspace Dripstud wall wrap was missing in the tender documents. None of the tenderers requested for that information (i.e. no RFI) during the tender period. There was also no notice to tenderers(NTT) set out regarding this.

You have received a tag from Clean Construction Co. Ltd. on Building wrap item which state that, “The rate of $9/m2 provided for Building wrap under Carpentry trade is for Thermakraft  220  Watergate Plus Wall Wrap. The rate  shall   change  if  different material/specification will be specified.” The quantity for the building wrap in the Schedule of Quantity (SOQ) is 435m2.

•    Explain your reasoning in every decision you make in your evaluation process.

•    Make all necessary and reasonable assumptions for the missing information.