QBUS 3350 S2 2023 - Individual Assignment 2
Hello, dear friend, you can consult us at any time if you have any questions, add WeChat: daixieit
QBUS 3350 S2 2023 - Individual Assignment 2
Question 1: Project Networking (30 marks)
You have collected the following data on the critical activities of a new project your firm is considering. Your boss is interested in how long the project will take.
a) Develop an Activity on Node network based on the information you have collected. Each node should contain the following information. (8 marks)
b) How long do you anticipate the project will take? What is the critical path? (2 marks)
c) After discussions with your engineer, it has become clear that a finish-to-start lag was missing. A 4-week finish-to-start lag between activity B and D will add flexibility to the network. Will the introduction of the lag change the critical path? (5 marks)
d) Replicate the network in part a) using the Activity on Arc (AOA) method. (5 marks)
e) Clearly defining your objective and constraints, develop a linear programming model that determines the project duration. Use EXCEL SOLVER to solve the model. (15 marks).
Question 2: Resource Levelling (25 marks)
Your project manager provides you with the following information.
a) Draw the network, defining the critical path and project duration (5 marks)
b) Create a resource loading table and confirm the project duration if 6 machines are available. (5 marks)
c) If two machines break down simultaneously and will not be available for 2 weeks, revise the resource loading table using the minimum slack heuristic to determine how long the project duration might be. In 50 words or less write an explanation of how you applied the heuristic. (10 marks)
d) Is this the optimal solution? Why or why not? Demonstrate using a resource loading chart. (5 marks)
Question 3: Earned Value Management (40 marks)
a) Create an AON network for this project (5 marks)
b) Develop a time phased budget (baseline). Hint: refer to slide 22 of lecture 10 (12 marks) c) Create status reports for periods 4 through 7, showing EV, AC, PV, CV, SV based on the following actual data. (12 marks)
d) For period 4 & 7 compute the SPI, CPI and PCIB indexes. (6 marks)
e) Comment on the project status at the end of period 4 and 7 only and how it has progressed during these periods. (3 marks)
f) Forecast and explain EACf (2 marks)
Submissions
All answers are to be submitted on an appropriately identified EXCEL file QBUS3350_S2_2023_Individual_Assignment 2 SID.xlsx, with one question per sheet. For clarity, type your written answers in text boxes in your EXCEL file. The file should not be saved as a PDF. The Excel should be uploaded to Canvas at thislocation.
Marks
This assessment will be marked out of 100 and is worth 10% of your overall grade. Each of the three questions are work different marks.
Deadlines
The report is due on the Monday 6th November at 11:59 PM (beginning of Stuvac). Because the due date is different to that stated in the UoS Guide, you will not be able to apply for a simple extension or Special Consideration via the university portal. If you are unwell or have some other legitimate reason you will not be able to submit by the due date, then you will need to email me directly at simon.lori[email protected] with appropriate supporting
documentation and I will consider your situation. We will post the marks of those students who submit on or before the due date before the exam on the 20 November. The same cannot be said for studnt who submit late.
Late penalties
In the absence of any SC, assignments submitted after the due date will incur a 5% per day penalty for the first 10 days. Reports more than 10 days late will receive a mark of zero.
Word count & referencing
N/A
Academic integrity
You are encouraged to ask questions of teaching team and have discussions with fellow students about the task, but that is as far as any collaboration should extend. All your written work, research and analysis needs to be your own. All submitted Excel files will be checked using Turnitin.
Best of luck.